Silicon Almanac. Search Calendar Your desk
Fabs · Fab

Fab 62

Intel, Ocotillo campus, Chandler, Arizona, United States. Every field this record holds on the site, its note and every source, as the row states them.

Every figure links to its publisher What changed, and when →
01

The row

Operator
Intel · company page: Intel
Site
Fab 62
Location
Ocotillo campus, Chandler, Arizona, United States
Type
logic
Status
construction
Wafer
300 mm
Nodes
Intel 18A, Intel 14A
First output
not recorded
Announced investment
not recorded
Map position
33.28, -111.94, on the map

Sister fab to Fab 52 on the same Ocotillo campus; being fitted out to follow Fab 52 into 18A/14A production.

02

Sources

2 sources on this row, in the order the row lists them. The order carries no weight.

Intel newsroom - press kit: Intel builds Arizona · newsroom.intel.com

Intel's fab roadmap examined - Tom's Hardware · tomshardware.com

03

Capacity statements

No published capacity statement names this site. Blank is unpublished, not zero.

04

On this record

What this record changed on this row, newest first. Each day is the day this record changed, never the day a publisher said it. Followed: status, first output year, announced investment, operator, name, site and sources.

2026-08-13 · The row entered this record, with the status construction. · Source at entry: Intel newsroom - press kit: Intel builds Arizona · Source at entry: Intel's fab roadmap examined - Tom's Hardware

None of the fields followed here has changed since the row entered this record on 2026-08-13.