01
The row
- Operator
- Intel · company page: Intel
- Site
- Fab 52
- Location
- Ocotillo campus, Chandler, Arizona, United States
- Type
- logic
- Status
- operating
- Wafer
- 300 mm
- Nodes
- Intel 18A
- First output
- 2025
- Announced investment
- USD 20 billion
- Map position
- 33.28, -111.94, on the map
First high-volume Intel 18A fab; began production 2025.
02
Sources
2 sources on this row, in the order the row lists them. The order carries no weight.
Intel newsroom - press kit: Intel builds Arizona · newsroom.intel.com
Intel's Fab 52 is bigger than TSMC Arizona - Tom's Hardware · tomshardware.com
03
Capacity statements
No published capacity statement names this site. Blank is unpublished, not zero.